Project:
Boulder 75th Street WWTP Headworks, UV Disinfection and Digester Improvements

Owner: City of Boulder
Location: Boulder, Colorado
Start Date: August 2011
Value: $8,090,000

Scope:

  • Make improvements to upgrade aging equipment and facilities.
  • Eliminate risks associated with the use of gaseous chlorine and sulfur dioxide for disinfection.
  • Install new systems to optimize the treatment plant process.
  • Specific areas of improvement are the headworks, digesters, centrate storage tanks and the existing chlorine contact basin conversion to ultraviolet disinfection.

 

 

 